Dear

We hereby propose to furnish all materials and perform all
labor necessary for the completion of Davit Installation
of the following specifications:
* installation = ¼³Ä¡(¼³ºñ)/ specifications = ¼³°è ¸í¼¼¼­

* One No. 1000 lb. galvanized davit installed on seawall
* Four-way lifting bridle
* Three 2"x8" wood fenders anchored to the wall with 5'
rubber bumper strip on each.
* galvanized = ¾Æ¿¬À» ¾º¿î/ davit = (º¸Æ®, ´éÀ») ´Þ¾Æ¿Ã¸®´Â ±âµÕ
* seawall = ¹æÆÄÁ¦, ¹æÁ¶Á¦/ bridle = ±¼·¹/ fender = ¹æÇöÀç
* anchored to ~ = ~¿¡ °íÁ¤µÈ


This work is to be performed on Lot_____Blk________Sub.
Div.______ for (name of owner) , Owner, in accordance
with
the drawings and specifications submitted for the
above work. The total cost including state tax is (amount)
* in accordance with ~ = ~¿¡ µû¶ó¼­(ºÎÇյǰÔ)

Payments to be made as follows : the sum of (amount) to
be paid upon the approval of this contract and the balance
of (amount) upon the completion of the work.

Any alteration or deviation from the above specifications
involving extra cost of material or labor will only be executed
upon written orders for same and will become an extra charge
over the sum mentioned in this contract. All agreements must
be made in writing.
* alteration = º¯È­, °³Á¶/ deviation (from ~) = (~·Î ºÎÅÍ) ÆíÂ÷; ÀÏÅ»

Property lines shall be designated by substantial marks, by owner
or his certified engineer. The contractors shall not be liable, as regards
to
the completion of the work, for any delay which may be caused
by reason or on account of any strike of workmanship, any Act of God,
unavoidable accidents, inability to secure materials or to use materials
in the performance of the work by reason of laws or regulations of
the United States of America or the State of (state), or any other
circumstance beyond their control, other than the want of funds.
No such delay shall be deemed a default on the part of the contractors,
and, in the event of any such delay, the contractor's time limit for
performance of the work shall be correspondingly extended. Workmen's
Compensation
and Public Liability Insurance on the above work shall be
provided by the Contractor.
* certified = º¸Áõ(Áõ¸í/°øÀÎ)µÈ/ as regards (to) ~ = ~¿¡ °üÇÏ¿©
* on account of ~ = ~¶§¹®¿¡(~Çؼ­)/ workmanship = ¼Ø¾¾, ±â¼ú, ±â·®
* act of God = ºÒ°¡Ç×·Â/ want of ~ = ~ÀÇ ºÎÁ·(°á¿©, °áÇÌ)/ default = ºÒÀÌÇà
* correspondingly = ºÎÀÀÇÏ¿©, »ó´ëÀûÀ¸·Î, »óÀÀÇÏ¿©
* workmen's compensation = ³ëµ¿ÀÚ ÀçÇØ º¸»ó


This Contract shall be deemed null and void if not signed within thirty days.
* null and void = ¹«È¿ÀÇ
 
Respectfully submitted,
* respectfully = ¼ÕÀ­ »ç¶÷¿¡°Ô º¸³»´Â ÆíÁöÀÇ Á¤ÁßÇÑ ¸ÎÀ½¸»

ACCEPTED;
By____________________________ OWNER
Date__________________________